X, Y and Z can complete a piece of work individually in 6 hours, 8 hours and 8 hours respectively. However, only one person at a time can work in each hour and nobody can work for two consecutive hours. All are engaged to finish the work. What is the minimum amount of time that they will take to finish the work.
Correct Answer: (C) 6 hours 45 minutes
X, Y and Z can complete a piece of work individually in 6 hours, 8 hours and 8 hours respectively. Now, to finish the work in minimum possible time, we need to ensure that X is utilized the most, as he’s the most efficient worker. So, we will use X alternatively every second hour. We will also start with him. So, the sequence of their working will be X, (Y or Z), X, (Y or Z), X, …..and so on. X can complete the work in 6 hours. So, in one hour he can complete 16.67% of the work. Similarly, Y (or Z) can complete the work in 8 hours. So, in one hour he can complete 12.5% of the work. Now, X + Y + X + Y + X + Y = 3X + 3Y = 50 + 37.5 = 87.5% Now, 12.5% of the work is left and it’s X’s turn to do it. X can do it in (12.5/16.67) hours, i.e. 0.75 hours, or 45 minutes. So, the entire task can be done by them in the minimum possible time of 6 hours 45 minutes. 8 www.visionias.in ©Vision IAS